Intermodal Station Phasing Plan
— by Jeffrey Wisniewski — 12 January 2010 — Comments Off
The staff report for BCDC’s initial design review of the Intermodal Station included an outline of construction phases, as well as a corresponding and somewhat complex figure that shows the construction phasing of station elements in plan (click image to enlarge)…
Two items of note…
- the transit plaza and cafe building will be part of the second phase, so presumably not concurrent with the construction of the station; and
- the permanent parking garage (Block K) is part of Phase 5, lumped in with the ferry connection, which is presumably far, far into the future. (I had assumed, however naively, that the permanent parking structure would follow shortly after the station, and the interim parking lot would be much more temporary.)


No comments yet …
Trackbacks so far …